Money and business in the Middle East.

AI Infrastructure

Khazna DXB2 (Dubai Design District) and DXB3 (Ibn Battuta)

United Arab Emirates · Data centre · Under construction (completion not confirmed) · Dubai Design District and Ibn Battuta, Dubai · Announced Oct 2022 · Target (as announced) Q3 2023 (DXB2) and Q1 2024 (DXB3), as stated in Oct 2022 · Khazna Data Centers

Two Khazna data centres in Dubai: DXB2 in Dubai Design District and DXB3 in Ibn Battuta. Khazna broke ground on them in October 2022, with a joint 43 MW of IT load, and said they would begin operations in Q3 2023 and Q1 2024. It has published no start-of-operations date for either site; an undated Khazna sustainability page lists both among its LEED Gold–certified facilities.

khaznadatacenters.com ↗

Target date passed (Q3 2023, Q1 2024, Oct 2022); INXEN has no confirmation of completion.

Overdue: Khazna said on 11 Oct 2022 that DXB2 and DXB3 "will begin operations in Q3 2023 and Q1 2024, respectively"; it has published no start-of-operations or revised date. Its undated sustainability page lists "LEED Gold certification for facilities including AUH6, DXB2, and DXB3". (checked 5 Oct 2026)

Verified · updated 4 Oct 2026

Key facts

43 MW

Announced capacity

Khazna Data Centers·as announced Oct 2022 (combined)·source dated 11 Oct 2022·updated 4 Oct 2026·About this indicator

Ownership and relationships

Ask INXEN

Sources

  1. Khazna Data Centers · khaznadatacenters.com